Join Our Team Login Ops Center

1200 Third Data Center

Seattle, WA

MacDonald-Miller: Mechanical Contractor

This 69,000 sq. ft. project entailed constructing the shell and core for the 13-story remodel as well as tenant improvements on seven floors.

Project Overview
  • Many systems were installed including condenser water, generator cooling water, fuel oil, and cooling towers.
  • TRemote radiators for generators were put in along with two 3,000-gallon fuel tanks and pump rooms

Activate.net

Seattle, WA

MacDonald-Miller: Mechanical Engineer and Mechanical Contractor

The 20,500 sq. ft. build-out created two areas, the Broadcast Operations Center (BOC) and the surrounding office space. The BOC area, built on a 24"" raised floor, contains all the server racks and user consoles.

Project Overview
  • Substantial cooling required for the BOC necessitated a condenser water system, which utilized eight Liebert water-cooled computer room AC units (200 tons total) and two open cooling towers (580 GPM each).
  • The open/closed condenser water loops use 580 GPM centrifugal pumps and a pair of plate and frame heat exchangers.
  • The surrounding office space is cooled by a 30-ton water-cooled Mammoth AC unit, which pumps 11,000 CFM of air through exposed ductwork.
  • Each zone has eleven VAV boxes and two cooling-only water source heat pumps that supplement the cooling for the heat generating UPS and LAN/TELCO rooms.

Amazon.com Main Data Center

Seattle, WA

MacDonald-Miller: Mechanical Engineer and Mechanical Contractor

This renovation included designing and installing 380 tons of computer room air conditioning equipment in four phases within 45,000 sq. ft. in an existing six-story building.

Project Overview
  • 40 tons of cooling equipment supper the UPS area, while 20 tons were used for the HVAC system.
  • All the equipment has "Econo-Coils" which give free cooling during winter operation.
  • A custom pre-fabricated dual pump package and large evaporative fluid cooler were also a part of the system.
  • All cooling equipment was furnished with alternator/alarm centralized control panels and auto flow/motorized shutoff valves.

AT&T

Bothell, WA

MacDonald-Miller: Mechanical Engineer and Mechanical Contractor

This remodel combined two buildings to create a 140,000 sq. ft. support center for AT&T. 50,000 sq. ft. is dedicated to the mechanical and electrical room space.

Project Overview
  • The HVAC system utilizes a 2,200-ton chilled water plant with four 550-ton water cooled chillers and cooling towers.
  • Two 30,000-gallon water storage tanks provide up to 72 hours of backup water to the facility, while humidity control is provided through a central ventilation/humidification air handler unit.

MCI Data Center

Kent, WA

MacDonald-Miller: Mechanical Contractor

Built on an aggressive six-week schedule, this project encompassed the installation and pipes for 84 computer room air conditioner (CRAC) units.

Project Overview
  • The computer room floor is cooled by the 84 CRAC units which each have 28 tons of cooling capacity.
  • Support rooms are conditioned using packaged rooftop air units, ranging in size from 10 to 120 tons.

Qwest Computer Center

Tukwila, WA

MacDonald-Miller: Mechanical Engineer and Mechanical Contractor

This 72,900 sq. ft. project provided the mechanical systems for the Internet hosting site for Qwest Communications.

Project Overview
  • The computer rack area uses 10 90-ton VAV Trane rooftop Intellipack air conditioning units, which are connected to a common 60" diameter duct loop around the entire floor area with over 200 variable air volume terminals.
  • N+1 redundancy is provided for the entire system.
  • The utility area houses batter and UPS systems that require special exhaust installations.
1200 Third Data Center

1200 Third Data Center
Seattle, WA